You are the project manager of the NHA Project. This project is expected to last one year with quarterly milestones throughout the year. Your project is supposed to be at the third milestone today but you're likely only 60 percent complete. Your project has a BAC of $745,000 and you've spent $440,000 of the budget- to-date. What is your schedule performance index for this project?

A. 80

B. 1.02

C. 102

D. 0.80

Buy Now
Questions 5

You are working with your project team to identify the project activities within your project. Which of the following is NOT a tool and technique that will be useful in defining the project activities?

A. Decomposition

B. Rolling wave plan

C. Precedence diagramming method

D. Templates

Buy Now
Questions 6

You are the project manager of the NHQ project. Your project has a budget of $1,258,456 and is scheduled to last for three years. Your project is currently forty percent complete though it should be forty- five percent complete. In order to reach this point of the project, you have spent $525,000. Management needs a performance report regarding the NHQ project. What is the planned value for this project?

A. $566,305

B. $1,258,456

C. -$54,044

D. $503, 382

Buy Now
Questions 7

Tom is the project manager for the ABC Construction Company. As part of the project scheduling for the construction of a new office building, he has allotted time for the inspectors of the building structure, as well as electrical, plumbing, and safety into the project's schedule. These inspectors can be considered what type of dependency in the project?

A. Mandatory dependencies

B. Required dependencies

C. Discretionary dependencies

D. External dependencies

Buy Now
Questions 8

You are the project manager for your organization. Your project is doing fine on time and cost, but management wants to address the project performance for future accomplishment. Management has asked you to begin reporting and forecasting your project's health based on a moving average, extrapolation, trend estimation, and growth curve. What type of forecasting method is management asking you to use?

A. Judgmental methods

B. Causal/econometric methods

C. Time series methods

D. Estimate at completion method

Buy Now
Questions 9

You work as a project manager for BlueWell Inc. You and your project team is undergoing the decision making process for the project. You want to involve key participants to gain acceptance and commitment to make the solution work. Which of the following phases of the decision- making model defines this process of work?

A. Ideas to action

B. Problem definition

C. Problem solution generation

D. Solution action planning

Buy Now
Questions 10

Gary is the project manager for his organization. The projects that Gary manages for project customers are often very similar in nature so Gary uses a schedule network template to help plan the project work. For Gary's current project, he has used a network template that includes just a portion of the project work adapted to the current project. When Gary uses a portion of a network template diagram this is called what term?

A. Analogous

B. Hanger

C. Fragment network

D. Parametric

Buy Now
Questions 11

You are the project manager of the NHA Project. This project is expected to last one year with quarterly milestones throughout the year. Your project is supposed to be at the third milestone today, but you are likely to be only 60 percent complete. Your project has a BAC of $745,000 and you have spent $440,000 of the budget-to-date. What is your schedule variance for this project?

A. $11,667

B. 1.02

C. $7,000

D. $-111,750

Buy Now
Questions 12

You are the project manager for your organization. You are coaching Allen, a junior project manager, on how the details of the project's critical path are calculated. Examine the figure given below:

What is the critical path of this project?

A. ABEHJ

B. ACFGJ

C. ADGJ

D. ACFIJ

Buy Now
Questions 13

You are the project manager for your organization. You want to record some details about the work that the project team has to complete. You want to document the level of effort, where the work is to be performed, and the person who will be responsible for completing the work. Which of the following is the best place to document this information?

A. Activity attributes

B. Project management plan

C. Schedule Management Plan

D. Roles and Responsibilities Matrix

Buy Now
Exam Code: PMI-SP
Exam Name: PMI Scheduling Professional (PMI-SP)
Last Update: Feb 17, 2025
Questions: 323
10%OFF Coupon Code: SAVE10

PDF (Q&A)

$49.99

VCE

$55.99

PDF + VCE

$65.99