A project in the execution phase is over budget, and tasks on the critical path are on schedule. Which of the following should the project manager do NEXT?
A. Update the project management plan.
B. Issue a change request.
C. Revise the project charter.
D. Evaluate the impact to the baseline.
A customer has requested additional features for an active project. Which of the following steps should take place NEXT?
A. Implement the requested changes.
B. Evaluate the impact of the changes.
C. Update all project documents.
D. Submit the requested changes to the CCB.
A new stakeholder has joined the project team and requested modifications that will result in minor changes to the project budget and schedule.
The project manager is concerned that the requests will lead to:
A. quality control issues.
B. additional risks.
C. scope creep.
D. time constraints.
Which of the following inherently affects quality standards?
A. SLA
B. MOA
C. MOU
D. WBS
Which of the following should be included in an effective SOW?
A. Lessons learned
B. Procurement process
C. Corrective action plan
D. Project objectives
A project manager detects a defect in a project deliverable and suspects a team member missed a step during production.
Which of the following tools would be BEST for the project manager to use to confirm this suspicion?
A. Pareto chart
B. Process diagram
C. Run chart
D. Fishbone diagram
A project manager is overseeing a project to analyze large amounts of data to find customer preferences. The large data sets are hosted by an external provider, and the project manager is concerned about losing access to the data.
Which of the following documents is appropriate for use in this situation?
A. Project schedule
B. Risk register
C. Action item log
D. Issue log
A project team member informs the project manager that a task on the critical path will not be completed on time.
Which of the following documents will MOST likely be updated? (Choose two.)
A. Project scope
B. Project charter
C. Project schedule
D. Risk register
E. Incident response plan
F. Communication plan
According to best practices, the average duration of a Scrum sprint should be:
A. one to five weeks.
B. two to four weeks.
C. two to four months.
D. one to five months.
The problem statement of a project helps to identify:
A. roadblocks impeding project progress
B. a connection to a larger program
C. a reason or purpose
D. start and end dates