Leads4pass > CompTIA > CompTIA Project+ > PK0-003 > PK0-003 Online Practice Questions and Answers

PK0-003 Online Practice Questions and Answers

Questions 4

Which of the following scheduling algorithms establishes floats, durations, and paths between work schedule activities?

A. AON

B. PERT

C. CPM

D. GERT

Buy Now
Questions 5

The project manager has noticed that meeting attendance rates are declining. Regular attendees prefer to talk about the past or upcoming weekend as opposed to reporting on project updates. Which of the following shows how the project manager should respond?

A. Take no action. Team bonding is important. Those that cannot attend are probably attending more important meetings as this project is not the only initiative within the organization.

B. Change the meeting format to be a daily stand-up of no longer than 15 minutes.

C. Escalate non attendance to functional line managers. Cut off non-related discussions.

D. Establish ground rules, distribute an agenda, and use a facilitator.

Buy Now
Questions 6

The project manager has had a large number of change requests approved by the project steering committee, but has been given no extra time to deliver the project. Which of the following schedule compression techniques should be used by the project manager?

A. Rescheduling

B. Crashing

C. Rebaselining

D. Control scope

Buy Now
Questions 7

Which of the following activity sequencing techniques uses nodes to symbolize the dependencies of each activity?

A. Critical Path Method

B. Critical Chain Method

C. Arrow Diagramming Method

D. Gantt Chart Method

Buy Now
Questions 8

When looking for solutions, which of the following procurement documents should be used?

A. CDM

B. CCM

C. RFI

D. RFQ

Buy Now
Questions 9

Which of the following tasks are performed within the initiation phase?

A. Create a WBS

B. Create a budget

C. Create a risk register

D. Create a charter document

Buy Now
Questions 10

A project starts out as a small three month project. One month into the project, a stakeholder asks the team for additional functionality, which is estimated to take an additional three weeks. The project manager implements the functionality while waiting for approval. This is known as which of the following?

A. Change request

B. Risk

C. Resource constraint

D. Scope creep

Buy Now
Questions 11

Which of the following is a zero time activity?

A. Milestone

B. Critical path

C. Deliverable

D. Work package

Buy Now
Questions 12

Which of the following represents the purpose of performing qualitative risk analysis?

A. To prioritize risks

B. To identify risk owners

C. To determine contingency reserves necessary

D. To identify new risks

Buy Now
Questions 13

Which of the following would be found in a transition plan? (Select TWO).

A. Key milestones

B. Project acceptance criteria

C. Training requirements

D. Tollgate approvals

E. Extended support

Buy Now
Exam Code: PK0-003
Exam Name: CompTIA Project+ (2009)
Last Update: Nov 22, 2024
Questions: 320
10%OFF Coupon Code: SAVE10

PDF (Q&A)

$49.99

VCE

$55.99

PDF + VCE

$65.99