You customer has completed a successful proof of Concept (PoC) consisting of a single frame with dual composers and virtual Connect SE 40GB F8 modules. The customer wants to: *add a second frame before they move into production *have unified management *have separate logical enclosure for each frame
What are basic steps to add the second frame?
A. Move the standby composer to the second frame
B. Disconnect the existing management ring, and then cable the FLM (frame link module) in the first frame to the FLMs in the second frame
C. install a satellite module in the first frame
D. Move the bottom VC module from the first frame to the second
E. Move one of the uplinks from the FLM in the first frame to a FLM in the second
A customer needs a Synergy proof of Concept (PoC) image Streamer. What is the minimum number of Synergy frame needed for this PoC?
A. 1
B. 2
C. 3
D. 5
A retail customer's real-time analytics application requires the fastest possible data access and over
768GB of database capacity. Their current HPE Proliant DL 380 Gen9 servers are not meeting the
performance requirements.
What should you recommend? ( select two.)
A. ILO 5 Advanced license
B. HPE Scalable persistence memory
C. HPE proliant DL380 Gen10 servers
D. PCIe workload Accelerator
You want to from synergy management ring. Which component is required?
A. HPE Synergy image Streamer
B. HPE Synergy frame Link Module
C. HPE Synergy Composer
D. HPE Synergy 10 GB interconnect Link Module
A customer considering installing a synergy frame in an existing rack where c7000 chassis is currently installed.
Which question should you ask to ensure the new frame will be supported in the rack?
A. Are there any third party server installed?
B. How deep is existing rack?
C. is there a UPS installed in the rack?
D. How wide is the existing rack?
Match each Synergy component with the description of the functionality it provides.
A. Answer:
A financial customer has a remote office that requires a significant amount of computing resources, but has no local IT staff. They need simple and affordable management and disaster recovery of their site.
Which solution should you recommends meet this customer's need?
A. HPE ConvergedSystem 300
B. HPE Simplivity 380
C. HPE StoreOnce 5100
D. HPE Serviceguard for Linux
A customer wants to implement HP Synergy with 20GP connectivity. What should architect emphasize during meeting with this customer?
A. A maximum frames can be slacked together when 20GB connectivity is required
B. SAS connectivity must be installed in each frame
C. A Composer must be installed in each frame
D. 20 GB connectivity will require additional license applied to the downlink ports
You need to demonstrate the runtime firmware verification scan functionality on a proLiant DL380 Den 10 server. You find that the option is not available in the UEFI interface.
A. The server boot I set UEFI.
B. The Onboard Administrator has been initialized.
C. The file firmware-O05-1-10.1.1.x86_64rpm is the incorrect version.
D. The required ILO license has been installed
While installing a three frame Synergy solution, only two of the frames are identified during the discovery
process.
What should you do to get resolution?
A. Remove and re-insert the standby Composer.
B. Issue a refresh command to the enclosure.
C. Open the front panel Composer, and read the error message.
D. Validate Frame link Module topology.