Leads4pass > EXIN > Exin Certification > EX0-002 > EX0-002 Online Practice Questions and Answers

EX0-002 Online Practice Questions and Answers

Questions 4

Which should be funded by a change budget?

A. Increase in agreed scope

B. Initiation stage

C. Change Authority

D. Handover activities

Buy Now
Questions 5

Which statement about stages is true?

A. Management stages should be of the same duration

B. The use of technical stages is mandatory

C. The use of management stages is mandatory

D. Management stages are driven by specialist teams

Buy Now
Questions 6

Which of the following is NOT an event-driven control?

A. Project mandate

B. Checkpoint Report

C. Exception Report

D. End of a stage

Buy Now
Questions 7

Which is a type of issue?

A. An expected dis-benefit

B. An off-specification

C. A project outcome

D. A scope tolerance

Buy Now
Questions 8

Which theme provides the controls to escalate any forecast beyond tolerance to the next management level?

A. Business Case

B. Plans

C. Progress

D. Quality

Buy Now
Questions 9

What process is used by the Project Board to respond to an Exception Report?

A. Controlling a Stage

B. Managing a Stage Boundary

C. Managing Product Delivery

D. Directing a Project

Buy Now
Questions 10

Which product is NOT created in the Managing a Stage Boundary process?

A. Benefits Review Plan

B. End Stage Report

C. Lessons Report

D. Exception Plan

Buy Now
Questions 11

Which is an objective of the quality review technique?

A. To baseline a product

B. To provide a common understanding of what products a project will create

C. To define the quality methods required within a project

D. To determine the quality responsibilities of a project team

Buy Now
Questions 12

What product identifies the management stages and other major control points in a project?

A. Business Case

B. Project Plan

C. Work Package

D. Project Brief

Buy Now
Questions 13

Which of the following statements about customer's quality expectations and acceptance criteria are true?

1.Customer's quality expectations form a specific and precise list of Acceptance criteria are often expressed in broad terms as a means to gain common understanding of general quality requirements.

2.Measurable criteria that a project product should meet in order to be acceptable to key stakeholders,

A. Only 1 is true

B. Only 2 is true

C. Both 1 and 2 are true

D. Neither 1 or 2 are true

Buy Now
Exam Code: EX0-002
Exam Name: PRINCE2 FoundationExam
Last Update: Dec 18, 2024
Questions: 149
10%OFF Coupon Code: SAVE10

PDF (Q&A)

$49.99

VCE

$55.99

PDF + VCE

$65.99