You are about to release a test progress report to a senior manager, who is not a test specialist. Which of the following topics should NOT be included in the test progress report? 1 credit
A. Product risks which have been mitigated and those which are outstanding.
B. Recommendations for taking controlling actions
C. Status compared against the started exit criteria
D. Detailed overview of the risk-based test approach being used to ensure the exit criteria to be achieved
Explain how the above mentioned report may differ from a report that you produce for the project manager, who is a test specialist Select TWO items from the following options that can be used to report to the project manager and would not be included in a report to senior management. 1 credit
A. Show details on effort spent
B. List of all outstanding defects with their priority and severity
C. Give product risk status
D. Show trend analysis
E. State recommendations for release
The introduction of reviews and inspections has often failed as a process improvement action. Identify the THREE most important measures that should be taken to reduce the risk that this test process improvement will fail. 2 Credits (for 2 out of 3 correct 1 credit)
A. Process ownership and experienced moderators who drive the inspection process.
B. Management support
C. Training of those involved
D. The availability of stands and processes
E. Usage of a more traditional software development lifecycle
F. Alignment with software process improvement
G. Using a reference model, e.g. TMMi
Which of the following would you least expect to form part of the analysis of initial tool costs? 1 credit
A. Integration with other tools
B. Learning time required to use the new tool
C. Tool portability
D. Evaluation of suitable tools
Which of the following would you expect to see in the master test plan? 1 credit
A. A description of how the test cases are cross-referenced to requirements in the test management tool.
B. A detailed identification of the resources that will carry out structural testing in the first iteration.
C. The test approach that will be applied at system integration testing.
D. A list of the names of the testers who will carry out the performance testing for the final iteration.
Which of the following team roles would be most appropriate to enhance the team and why? 2 credits
A. A person with the ability to complete tasks
B. A quality assurance officer
C. A person with in-depth technical skills
D. A person who brings new ideas to the team
Evaluate the status of the project against the defined exit criteria. Which of the following options shows the correct status? 2 credits
A. Criteria A = OK, criteria B = OK, criteria C = OK
B. Criteria A = NOT OK, criteria B = NOT OK, criteria C = OK
C. Criteria A = OK, criteria B = NOT OK, criteria C = NOT OK
D. Criteria A = NOT OK, criteria B = NOT OK, criteria C = NOT OK
In general which part of the testing activity is most difficult to estimate? 1 credit
A. Test planning
B. Test execution
C. Test management
D. Test design
Comparing TMMi and TPI, which is not a valid reason for choosing either TPI or TMMi? 2 credits
A. If the scope of test performance improvement covers all test levels, TMMi is preferred since TPI focusses mainly on black-box testing.
B. If the organization is already applying CMMI, TMMi may be preferred since it has the same structure and uses the same terminology. TMMi addresses management commitment very strongly and is therefore more suitable to support a top-down improvement process.
C. TPI is much more a bottom-up model that is suitable for addressing test topics for a specific (test) project.
D. TMMi can only be used with the traditional V model,whereas TPI can be used with all types of software life cycles.
Continuing with the Scenario described in the previous question, which of the following topics would you need to address in detail in the master test plan? 3 credits
A. An approach to regression testing
B. A list of boundary values for "advance amount"
C. A description of dependencies between test cases
D. A logical collection of test cases