Questions 4

What type of planning is used where the work to be accomplished in the near term is planned in detail, while work in the future is planned at a higher level?

A. Finish-to-start planning

B. Rolling wave planning

C. Short term planning

D. Dependency determination

Buy Now
Questions 5

Organizational planning impacts projects by means of project prioritization based on risk, funding, and an organizations:

A. Budget plan

B. Resource plan

C. Scope plan

D. Strategic plan

Buy Now
Questions 6

Which schedule compression technique has phases or activities done in parallel that would normally have been done sequentially?

A. Crashing

B. Fast tracking

C. Leads and lags adjustment

D. Parallel task development

Buy Now
Questions 7

Which of the following response strategies are appropriate for negative risks or threats?

A. Share, Accept, Transfer, or Mitigate

B. Exploit, Enhance, Share, or Accept

C. Mitigate, Share, Avoid, or Accept

D. Avoid, Mitigate, Transfer, or Accept

Buy Now
Questions 8

The project charter is an input to which process?

A. Develop Project Charter

B. Develop Project Management Plan

C. Monitor and Control Project Work

D. Perform Integrated Change Control

Buy Now
Questions 9

What are the key components of the communication model?

A. Encode, message and feedback-message, medium, noise, and decode

B. Encode, messaging technology, medium, noise, and decode

C. Sender, message and feedback-message, medium, noise, and translate

D. Receiver, message and feedback-message, medium, noise, and decode

Buy Now
Questions 10

What scope definition technique is used to generate different approaches to execute and perform the work of the project?

A. Build vs. buy

B. Expert judgment

C. Alternatives identification

D. Product analysis

Buy Now
Questions 11

A contractor has provided hands-on training to a team member on new equipment that has been purchased as part of the project. The team member has acquired key insight and experience on the new equipment.

What is this an example of?

A. Explicit knowledge

B. Formal education

C. Tacit knowledge

D. Lessons learned

Buy Now
Questions 12

A project manager needs to tailor the Project Cost Management process. Which considerations should the project manager apply?

A. Diversity background

B. Stakeholder's relationships

C. Technical expertise

D. Knowledge management

Buy Now
Questions 13

DRAG DROP

Match the method for categorizing stakeholders with its corresponding description.

Select and Place:

Buy Now
Exam Code: CAPM
Exam Name: Certified Associate in Project Management (CAPM)®
Last Update: Dec 20, 2024
Questions: 1470
10%OFF Coupon Code: SAVE10

PDF (Q&A)

$49.99

VCE

$55.99

PDF + VCE

$65.99