What is one of the MAJOR outputs of activity sequencing?
A. Responsibility assignment matrix
B. Work breakdown structure update
C. Project network diagram
D. Mandatory dependencies list
Which is one of the determining factors used to calculate CPI?
A. EV
B. SPI
C. PV
D. ETC
At which point of the project is the uncertainty the highest and the risk of failing the greatest
A. Final phase of the project
B. Start of the project
C. End of the project
D. Midpoint of the project
What is included in a control chart?
A. Baseline
B. Planned value
C. Upper specification limit
D. Expenditure
Who has the responsibility for informing the final deliverable to all stakeholders?
A. Project Manager
B. Sponsor
C. Team Lead
D. Management
Create Procurement document is done in .
A. Plan Procurements
B. Conduct Procurements
C. Administer Procurements
D. Close Procurements
If a project with a SPI of 0.8, what you tell?
A. The project is running ahead of the schedule
B. The project is running behind of the schedule
C. Resources assigned to the project cost 1.8 units
D. None
The project management plan:
A. Identifies all the steps and processes that will be used after a project is initiated
B. Steps needed to complete a project task
C. Prepared at the beginning and fixed throughout the execution of the project
D. Includes project charter
You are the project manager of a project. Project is installing AC to hotel rooms. You have done project cost and time estimates, told the customer that the estimates provided will be accurate if the rooms meet the requirements like (wooden coated). This is an example of which of the following?
A. Risk
B. Assumption
C. Constraint
D. Budget
A scope management plan In which of the following scope management processes is the scope management plan prepared?
A. Initiation
B. Collect Requirements
C. Define Scope
D. Verify Scope