Which time elements are relevant for lead time scheduling of a production order? (Choose 2)
A. Float after production
B. Planned delivery time
C. Total replenishment lead time
D. Setup time
Which alternative item strategies are available in bills of materials (BOM) in SAP S/4HANA? (Choose 2)
A. First in first out (FIFO)
B. 100% check
C. Simultaneous
D. By usage probability
Which information is required when you created a production master in SAP S/4HANA? (Choose 2)
A. Selective screen for views
B. Product type
C. Base unit of measure
D. Industry sector
You want to use capacity availability checks for production orders. Which settings have to be made for this? (Choose 2)
A. A checking rule must be assigned in the checking control
B. The PRT Availability Check must be set in the checking control.
C. An overall profile must be assigned in the checking control.
D. The Relevant for Finite Scheduling indicator must be set
What do you use to dispatch operations from planned orders so that the production plan can be fulfilled?
A. Material Requirements Planning (MRP)
B. Capacity Requirements Planning (CRP)
C. Supply Network Planning (SNP)
D. Demand Planning (DP)
Which of the following processes lead to an entry in the MRP planing file? (Choose 3)
A. Change of the material's procurement type
B. Creation of purchasing contract
C. Creation of dependent requirements
D. Creation of sales order
E. Change of the storage bin
Your company produces a finished good based on a forecast and expects it to being stock when customers order it. If customers order more than the forecasted quantity, the production quantity should be increased to try to meet the extra demand.
Which planning strategy do you use?
A. Planning with final assembly (40)
B. Make-to-order production (20)
C. Make-to-stock production (10)
D. Planning without final assembly (50)
What happens to this dependent requirement when you convert the planned order into a production order?
A. They are converted into a schedule line.
B. They are converted into a reservation.
C. They are converted into a production order.
D. They are converted into a planned order.
How can you achive a feasible production plan in case of capacity constraints? (Choose 3)
A. Select an alternative mode on a resource.
B. Adjust the available capacity.
C. Reduce the planning window
D. Form optimum sequence to reduce setup times
E. Execute an infinite production planning run
What detremines whatherthe planned independent requirements in MRP are consumed by other requrements?
A. Consumption sequence procedure
B. Requirements profile
C. Order type
D. Requirements type