Which of the following cost planning transactions are related to Account assignment? There are 3 correct
answers to this question.
Response:
A. Invoice posting
B. Goods movement
C. Confirmations
D. Purchase requisitions
Which version serves as a proof of the project status in the past and also serves as a comparison with the
operative project? Please choose the correct answer.
Response:
A. Operative version
B. Simulation version
C. Project version
D. Milestone version
Workforce Planning in Project Systems, allows you to assign certain HR resources to activities of a project.
Which of the following can be assigned?
There are 3 correct answers to this question.
Response:
A. Persons
B. Organizational units
C. Jobs
D. Positions
Which of the following costs are automatically calculated based on the resource requirements identified for activities and operations when using networks and activities? Please choose the correct answer.
A. Manual costs
B. Actual costs
C. Planned costs
D. Element costs
In progress tracking what are the different ways of assigning the dates of events that are assigned to network components while evaluation? There are 3 correct answers to this question.
A. Using BADIs
B. Generation and assignment of a new event
C. Direct assignment of a new event
D. Direct assignment of a standard event
Assume you have information on sources of supply, quantities, and prices and you have decided to use unit costing to produce a cost plan per WBS element. Which of the following costs can be planned? There are 3 correct answers to this question.
A. Each material
B. Cost element level
C. Internal service
D. Each internal activity
How do you reduce the scheduled duration of internally-processed activities if the time period within which the activities are to be scheduled is not long enough to process all activities? Please choose the correct answer.
A. Milestones
B. Capacity breech
C. Reduction
D. Scheduling breech
Which of the following are controlled using plant and order type parameters? There are 2 correct answers to this question.
A. The settlement rule strategy
B. Number assignment
C. Default value settings
D. If the network is assigned to an activity or header
How are cost-relevant items determined for stock materials while using planned costs in networks? Please
choose the correct answer.
Response:
A. Activity master record
B. Activity detail screen
C. Overhead costs screen
D. Automatic account determination
Assume a scenario where deviations from the project plan occurred as a result of delivery problems, price fluctuations, and unforeseeable capacity bottlenecks. How do you ensure that claims resulting from deviations are prepared for contractual partners and submitted to them at suitable point of time? Please choose the correct answer. Response:
A. Safety measures
B. Status management
C. Claim management
D. Actions