Which process numerically analyzes the effect of identified risks on overall project objectives?
A. Plan Risk Management
B. Plan Risk Responses
C. Perform Quantitative Risk Analysis
D. Perform Qualitative Risk Analysis
A regression line is used to estimate:
A. Whether or not a process is stable or has predictable performance.
B. How a change to the independent variable influences the value of the dependent variable.
C. The upper and lower specification limits on a control chart.
D. The central tendency, dispersion, and shape of a statistical distribution.
Which type of dependency is established based on knowledge of best practices within a particular application area or some unusual aspect of the project in which a specific sequence is desired, even though there may be other acceptable sequences?
A. External
B. Internal
C. Mandatory
D. Discretionary
The methodology that combines scope, schedule, and resource measurements to assess project performance and progress is known as:
A. Earned value management.
B. Forecasting.
C. Critical chain methodology.
D. Critical path methodology.
What is the probability of occurrence if the risk rating is 0.56 and the impact if the risk does occur is very high (0.80)?
A. 0.45
B. 0.56
C. 0.70
D. 1.36
Which of the following is an input to Direct and Manage Project Execution?
A. Requested changes
B. Approved change requests
C. Work performance information
D. Implemented defect repair
When is a Salience Model used?
A. In a work breakdown structure (WBS)
B. During quality assurance
C. In stakeholder analysis
D. During quality control (QC)
A method to manage stakeholder expectations in the scope statement is to clearly:
A. state the guiding principles of the organization.
B. identify alternatives to generate different approaches.
C. state what is out of scope.
D. outline the results of the Delphi technique.
As the project progresses, which of the following is routinely collected from the project activities?
A. Communication management activities
B. Change requests
C. Configuration verification and audit
D. Work performance information
Which tool within the Perform Quality Control process identifies whether or not a process has a predictable performance?
A. Cause and effect diagram
B. Control charts
C. Pareto chart
D. Histogram