Which tool or technique is an examination of industry and specific vendor capabilities?

A. Independent estimates

B. Market research

C. Analytical techniques

D. Bidder conferences

Buy Now
Questions 5

A project manager providing information to the right audience, in the right format, at the right time is an example of which type of communication?

A. Efficient

B. Effective

C. Push

D. Pull

Buy Now
Questions 6

Project deliverables that have been completed and checked for correctness through the Control Quality process are known as:

A. Verified deliverables.

B. Validated deliverables.

C. Acceptance criteria.

D. Activity resource requirements.

Buy Now
Questions 7

Project Stakeholder Management focuses on:

A. project staff assignments

B. project tea m acquisition

C. managing conflicting interests

D. communication methods

Buy Now
Questions 8

Managing ongoing production of goods and services to ensure business continues efficiently describes which type of management?

A. Portfolio

B. Project

C. Program

D. Operations

Buy Now
Questions 9

When is a Salience Model used?

A. In a work breakdown structure (WBS)

B. During quality assurance

C. In stakeholder analysis

D. During quality control (QC)

Buy Now
Questions 10

Which action should a project manager take to ensure that the project management plan is effective and current?

A. Conduct periodic project performance reviews.

B. Identify quality project standards.

C. Follow ISO 9000 quality standards.

D. Complete the quality control checklist.

Buy Now
Questions 11

Which type of analysis would be used for the Plan Quality process?

A. Schedule

B. Checklist

C. Assumption

D. Cost-Benefit

Buy Now
Questions 12

Which characteristic do projects and operational work share in common?

A. Performed by systems

B. Constrained by limited resources

C. Repetitiveness

D. Uniqueness

Buy Now
Questions 13

Which of the following are three inputs to the risk register?

A. Risk register updates, stakeholder register, and quality management plan

B. Communication management plan, enterprise environmental factors, and activity duration estimates

C. Risk management plan, activity cost estimates, and project documents

D. Project scope statement, organizational process assets, and scope baseline

Buy Now
Exam Code: APM-001
Exam Name: Certified Associate in Project Management (APM)
Last Update: Jan 04, 2025
Questions: 704
10%OFF Coupon Code: SAVE10

PDF (Q&A)

$49.99

VCE

$55.99

PDF + VCE

$65.99