The ProjectManager selects the "Update units when costschange on resource assignments"optionon Calculations tab in Project Details. The Budgeted Cost is $2,000 and the Budgeted Units is 80 for the resource on an activity. If the User assigns the activity an Actual Cost of $1,000, what is the Actual Units for the resource?
A. 70
B. 40
C. 60
D. 80
An activity is to be completed within a fixed time period and thetotalamount of work is fixed.
What duration type should be used?
A. Fixed Units
B. Fixed Duration and Units/Time
C. FixedUnits/Time
D. Fixed Duration and Units
What is the significance of the setting "Summarize project based on detailed activity resource assignments"?
A. Summarized project data will reflect Top Down plans.
B. Summarized project data will reflect Bottom Up plans.
C. Summarized project data will reflect integrated Actuals.
D. Summarized project data will be monetized.
You are a Resource Manager making resource assignments in P6 EPPM WebPlan Resources view. Youcan clearly see that the changes have been made. You move toanothersection of P6 EPPM Web, andreturn to the Plan Resources view, only to find that your changes have not beenretained.
What is the likely cause of this problem?
A. You selected over allocated resources for a project.
B. You assigned resources to a project to which you did not have security access.
C. You did not save before moving to the next screen, so changes were lost
D. The project data has become corrupt and will need to be rebuilt.
Select the true statement regarding Role proficiency.
A. The numbers and values can be customized.
B. User Defined Fields can be substituted for numbers and values.
C. The numbers and values cannot be customized.
D. Global Resource Codes can be substituted for numbers and values.
In addition to the four primary elements that comprise security, what additional feature in P6 Web will determine a user's access to data?
A. Portfolio Portlets
B. User Dashboards
C. User Interface View
D. Resources portlets
Identify the best definition of Funding Source.
A. Contributing source of funds for a project's financing are assigned in Project Details
B. Percentage of the total fund allocated to the project are created and managed at the Project level
C. Agency where funds will be allocated for the project
D. Removes unwanted portlets from the User Interface View
You are a Project Manager who is closing out a completed project. You have confirmed that all hoursthat should be charged to the project have in fact been charged. Youhaveconducted your LessonLearned activity. All parties agree that the projectiscomplete.
Which project status is the best choice for this project?
A. Active
B. Inactive
C. What-If
D. Planned
Select the statement that best describes a global portfolio.
A. It is available to single users.
B. It is assigned by a filter.
C. It must be manually refreshed.
D. It is available to all users.
E. Access is governed by security.
You are a Portfolio Manager with one project that is clearly underperforming. You would like to obtain more information about where the problems in the project reside.
How would you do this in PrimaveraP6 EPPM Web interface without contacting the Project Manager?
A. Click the project name to view performance data by Work Breakdown Structure (WHS).
B. Send an email asking for more information from the Project Manager.
C. Send an alert via workflow asking for more information from the Project Manager.
D. Createan Issue for follow-up by the Project Manager.